Las Positas Multiuse Path Update

The multiuse path along the Modoc stretch is beginning to take its shape! The contractor has installed approximately 3,600 linear feet of curb and gutter using a machine to facilitate its placement. The retaining curbs on both sides of the path have been constructed and the permeable aggregate base course (as shown in the photo above) will continue to be placed in segments.

Read More here > Las Positas Multiuse Path Update 12/14/20 PDF