Coast Village Circle Paving Project

Why this Project?

The January 2018 debris flow caused major road damage on Coast Village Circle, including significant asphalt erosion and concrete curb displacement, due to flooding and heavy equipment traffic during the emergency response. Repairs are necessary to restore the roadway to pre-disaster conditions. This year, Santa Barbara was awarded state and federal disaster assistance grants to complete this important repair work. In addition to new pavement along the entire length of Coast Village Circle, the Project will install new curb to improve drainage flow.

Project Overview PDF

What's Happening?

News Image

Phase 3 of Coast Village Circle Project Begins

October 14, 2019 

Phase 3 of the Coast Village Circle Pavement Rehabilitation Project is underway as of Monday, October 14. Phase 3 is scheduled to last 7 to 9 working days.

Please note the phase limits have been adjusted to accommodate driveway access as much as possible. Refer to “Project Overview PDF” for updated limits of work.

Coast Village Circle is closed to through traffic for the duration of the project. There is limited access for local traffic to businesses and properties on Coast Village Circle. For businesses that have access off Coast Village Road, access will not be impacted, and you may choose to access parking lots through this alternative.

Read More »

News Image

Phase 2 of Coast Village Circle Project Begins

September 30, 2019 

Phase 2 of the Coast Village Circle Pavement Rehabilitation Project is underway as of Tuesday, October 1st. Phase 2 is scheduled to last 7 to 9 working days. Please refer to the “Project Overview PDF” above for the limits of Phase 2 work.

Phase 1 was completed ahead of schedule and involved construction of concrete curb and replacement of the base and pavement layers.

Coast Village Circle is closed to through traffic for the duration of the project. There is limited access for local traffic to businesses and properties on Coast Village Circle.

Read More »

News Image

Phase 1 of Coast Village Circle Project Begins

September 23, 2019 

The Coast Village Circle Pavement Rehabilitation Project is officially underway as of Monday, September 23. The work will restore the road to pre-disaster conditions and is anticipated to last approximately two months, with completion expected in late November.

With Phase 1 of the five-phase project currently underway, Coast Village Circle is closed to through traffic for the duration of the project. There will be limited access for local traffic to businesses and properties on Coast Village Circle. Phase 1 work starts on the west side next to Coast Village Chevron and will last for approximately two weeks. Stay tuned for more updates as the project progresses.

Read More »