The January 2018 debris flow caused major road damage on Coast Village Circle, including significant asphalt erosion and concrete curb displacement, due to flooding and heavy equipment traffic during the emergency response. Repairs are necessary to restore the roadway to pre-disaster conditions. This year, Santa Barbara was awarded state and federal disaster assistance grants to complete this important repair work. In addition to new pavement along the entire length of Coast Village Circle, the Project will install new curb to improve drainage flow.

Project Overview PDF

What's Happening?

News Image

Phase 5 Begins

November 4, 2019 

Construction of the Coast Village Circle Pavement Rehabilitation Project is on schedule, with Phase 5 underway as of Monday, November 4.

Base paving for all five phases of the project will be complete by Friday, November 8, barring any unavoidable delays. The final paving course will be placed the week of November 11, during which time Coast Village Circle will be completely closed to vehicular traffic.

The newly paved road will be open on the afternoon of Friday, November 15.

Read More »

News Image

Phase 4 Begins

October 24, 2019 

Construction of the Coast Village Circle Pavement Rehabilitation Project is progressing and on schedule. Phase 4 was underway on Wednesday, October 23 with an approximate duration of 7 to 9 working days.

Phase limits have been adjusted as Phases 2 and 3 were extended slightly from the original design. Refer to “Project Overview PDF” for updated limits of work.

Read More »

News Image

Phase 3 of Coast Village Circle Project Begins

October 14, 2019 

Phase 3 of the Coast Village Circle Pavement Rehabilitation Project is underway as of Monday, October 14. Phase 3 is scheduled to last 7 to 9 working days.

Please note the phase limits have been adjusted to accommodate driveway access as much as possible. Refer to “Project Overview PDF” for updated limits of work.

Coast Village Circle is closed to through traffic for the duration of the project. There is limited access for local traffic to businesses and properties on Coast Village Circle. For businesses that have access off Coast Village Road, access will not be impacted, and you may choose to access parking lots through this alternative.

Read More »

Last Updated: Oct 23, 2019